Optimization of Flat Construction Implementation Time Using Critical Path Method and Project Evaluation and Review Technique
Abstract
This research aims to develop a system that effectively solves construction project management problems using PERT (Project Evaluation and Review Technique) and CPM (Critical Path Method) methods for the ASN flat construction project in Piru City, Maluku Province, Indonesia. In this study, the project activity data was analyzed using the PERT Method, which includes realistic, optimistic, and pessimistic durations; then, it is used to calculate the estimated time of each activity. Meanwhile, CPM was used to determine the critical path of the project. The results showed that project management can be done more accurately and efficiently with these two methods, minimizing the risk of delays. The optimal duration of the project obtained is 49 weeks with a probability value of 98.87% with the critical path obtained, namely A-B-E-F-G-J-K-L-M.
Downloads
References
Undang Undang No . 5 Tahun 1984 Tentang Perindustrian, “Undang Undang No . 5 Tahun 1984 Tentang Perindustrian,” Undang Undang No . 5 Tahun 1984 Tentang Perindustrian, no. 5, p. 3, 1984, [Online] ["Law No. 5 Year 1984 on Industry," Law No. 5 Year 1984 on Industry. 5 Year 1984 Regarding Industry," Law No. 5 Year 1984 Regarding Industry, no. 5, p. 3, 1984, [Online]. 5 Year 1984 About Industry, no. 5, p. 3, 1984, [Online]]. Available: https://jdih.kemenkeu.go.id/fulltext/1984/5TAHUN~1984UU.htm
I. Supriyanto, “Kebutuhan Dasar Perumahan Sehat yang Layak dan Teratur,” ["Basic Needs for Adequate and Organized Healthy Housing"] Media Penelit. dan Pengemb. Kesehat., vol. 7, no. 01, 1997.
E. Hermawan and R. Sulastri, “Pemberdayaan Masyarakat: Pentingnya Pemenuhan Kebutuhan Dasar Masyarakat,” ["Community Empowerment: The Importance of Fulfilling Basic Community Needs"] Distingsi J. Digit. Soc., vol. 1, no. 3, pp. 1–6, 2023.
V. Y. I. Ilwaru, D. L. Rahakbauw, and J. Tetimelay, “PENJADWALAN WAKTU PROYEK PEMBANGUNAN RUMAH DENGAN MENGGUNAKAN CPM (CRITICAL PATH METHOD),”[ "TIME SCHEDULING OF HOUSE BUILDING PROJECTS USING CPM (CRITICAL PATH METHOD)"] BAREKENG J. ILMU Mat. DAN Terap., vol. 12, no. 2, 2018, doi: 10.30598/vol12iss2pp061-068ar617.
Sugiannor, “Pengaruh Pembangunan Infrastruktur Fisik dalam Peningkatkan Kesejahteraan Masyarakat Desa Malintut Kecamatan Raren Batuah Kabupaten Barito Timur,” ["The Effect of Physical Infrastructure Development in Improving the Welfare of the Malintut Village Community, Raren Batuah District, East Barito Regency"] J. As Siyasah, vol. 5, no. 1, 2020.
S. Iman, Manajemen Proyek (Dari Konseptual sampai Operasional [Project Management (From Conceptual to Operational)]. Jakarta: Erlangga, 1999.
A. Abdurrasyid, L. Luqman, A. Haris, and I. Indrianto, “Implementasi Metode PERT dan CPM pada Sistem Informasi Manajemen Proyek Pembangunan Kapal,” ["Implementation of PERT and CPM Methods on Shipbuilding Project Management Information System"] Khazanah Inform. J. Ilmu Komput. dan Inform., vol. 5, no. 1, 2019, doi: 10.23917/khif.v5i1.7066.
A. Angelin and S. Ariyanti, “ANALISIS PENJADWALAN PROYEK NEW PRODUCT DEVELOPMENT MENGGUNAKAN METODE PERT DAN CPM,” ["ANALYSIS OF NEW PRODUCT DEVELOPMENT PROJECT SCHEDULING USING PERT AND CPM METHODS"] J. Ilm. Tek. Ind., vol. 6, no. 1, 2019, doi: 10.24912/jitiuntar.v6i1.3025.
N. M. Astari, A. M. Subagyo, and K. Kusnadi, “PERENCANAAN MANAJEMEN PROYEK DENGAN METODE CPM (CRITICAL PATH METHOD) DAN PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE),” ["PROJECT MANAGEMENT PLANNING BY CPM (CRITICAL PATH METHOD) AND PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE) METHODS"] Konstruksia, vol. 13, no. 1, 2022, doi: 10.24853/jk.13.1.164-180.
S. Raihan, A. Abiyyu, and E. Setiawan, “Analisis Network Diagram Dengan Metode Cpm Dan Pert Pada Project Pekerjaan Pemasangan Komponen Kelistrikan Kereta Listrik Makasar Pare-Pare,” ["Network Diagram Analysis with Cpm and Pert Methods on the Project of Electrical Component Installation Work for Makasar Pare-Pare Electric Train"] Simp. Nas. RAPI XXII, pp. 98–108, 2023.
R. Hidayah, A. Ridwan, and Y. Cahyo, “ANALISA PERBANDINGAN MANAJEMEN WAKTU ANTARA PERENCANAAN DAN PELAKSANAAN,” ["ANALYSIS OF TIME MANAGEMENT COMPARISON BETWEEN PLANNING AND EXECUTION"] JURMATEKS, vol. 1, no. 2, 2018, doi: http://dx.doi.org/10.30737/jurmateks.v1i2.416.
R. A. Husna, N. F. Ilmiyah, and N. C. Resti, “Implementasi CPM dan PERT dalam Memprediksi Durasi serta Biaya Pembangunan Musala Al-Ikhlas di Kotawaringin Barat,” ["Implementation of CPM and PERT in Predicting the Duration and Cost of Construction of Musala Al-Ikhlas in West Kotawaringin"] J. Focus Action Res. Math. (Factor M), vol. 5, no. 1, pp. 97–109, 2022, doi: 10.30762/f_m.v5i1.633.
S. R. Jannah, L. Muzdalifah, and E. F. Kurniawati, “Optimasi waktu penjadwalan proyek pembangunan perumahan menggunakan Critical Path Method (CPM) /Program Evaluation and Review Technique (PERT) dan Simulasi Monte Carlo (Studi Kasus CV. Granada Property),” ["Optimization of housing construction project scheduling time using Critical Path Method (CPM)/Program Evaluation and Review Technique (PERT) and Monte Carlo Simulation (Case Study CV. Granada Property)"] Pros. SNasPPM, vol. 3, no. 1, 2018.
R. Febriyannor, S. El Unas, and I. Wijatmiko, “Analisis Percepatan Pelaksanaan Pembangunan Dengan Menambah Jam Kerja Dan Tenaga Kerja Menggunakan Tracking Ms Project (Study Kasus: Rusunawa Buring 2, Gor Ken Arok - Malang),” ["Analysis of Acceleration of Development Implementation by Adding Working Hours and Labor Using Tracking Ms Project (Case Study: Rusunawa Buring 2, Gor Ken Arok - Malang)"] J. Mhs. Jur. Tek. Sipil Univ. Brawijaya, vol. 1, no. 2, 2016.
Rizkhon M F, Manajemen Penjadwalan Proyek Pembangunan Rusunawa Unnes Dengan Metode Pert Dan Mathcad [Scheduling Management of Unnes Rusunawa Construction Project with Pert and Mathcad Methods]. 2009.
Ardany, “Evaluasi Waktu Pekerjaan Dengan Menggunakan Metode PERT Pada Proyek Peningkatan Saluran Irigasi Bandara Syamsudin Noor,” ["Evaluation of Work Time Using PERT Method on Syamsudin Noor Airport Irrigation Channel Improvement Project"] J. Univ. Islam Kalimantan Muhammad Arsyad Al Banjari, 2020.
S. M. Iriyanto, D. Sopater, and Y. Oktovianus Hommy, “Analisa Perencanaan Waktu Dengan Metode Pert Pada Pelaksanaan Proyek Pembangunan Gedung Negara Provinsi Papua,” ["Analysis of Time Planning with Pert Method on the Implementation of the Papua Province State Building Construction Project"] Portal Sipil, vol. 6, no. 2, pp. 10–28, 2017.
Copyright (c) 2025 Adis Harni Tuanaya, Venn Yan Ishak Ilwaru, Yopi Andry Lesnussa
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
The author(s) hold the copyright of the published article without restriction. This policy means that the journal allows the author(s) to hold and retain publishing rights without restrictions.
The author(s) holds the copyright of published articles without limitation. This policy means that the journal allows the author to hold and retain publishing rights without restrictions. Journal editors are given the copyright to publish articles in according to agreement signed by the author and also include statement of originality of the article