SCHEDULING ANALYSIS BEDUGUL VILLA CONSTRUCTION PROJECT USING PERT AND CPM METHODS

  • Kiswara Agung Santoso Department of Mathematics, Faculty of Mathematics and Natural Science, Jember University, Indonesia
  • Ade Ratna Yusnita Department of Mathematics, Faculty of Mathematics and Natural Science, Jember University, Indonesia
  • Agustina Pradjaningsih Department of Mathematics, Faculty of Mathematics and Natural Science, Jember University, Indonesia
Keywords: PERT, CPM, Optimum Duration, Construction Scheduling

Abstract

Scheduling in construction projects is necessary so that the planned time to complete the project can be achieved on time. the methods used in optimizing project scheduling are the Project Evaluation Review Technique (PERT) method and the Critical Path Method (CPM) method. Bedugul  Villa is one of the projects that has been carried out with a work contract for 175 calendar days and the scheduling of which will be optimized in this study. The optimal duration for scheduling with the PERT method is to produce an optimal duration of 170 calendar days. The duration is 5 days faster than the existing schedule prepared by the project construction contractor, which is 175 calendar days. The probability of completion of the project is 87.7%. Calculations using the CPM method are 168 calendar days or 7 days earlier than the existing schedule made by the contractor.

Downloads

Download data is not yet available.

References

F. S. Wijaya and H. Sulistio, “PENERAPAN METODE MONTE CARLO PADA PENJADWALAN PROYEK SERPONG GARDEN APARTMENT,” JMTS: Jurnal Mitra Teknik Sipil, vol. 2, no. 3, p. 189, Oct. 2019, doi: 10.24912/jmts.v2i3.5828.

S. Ilham, I. Revo, and P. Pingkan, “Optimasi Penjadwalan Menggunakan Algoritma Genetika Pada Proyek Rehabilitasi Puskesmas Minanga,” Jurnal Sipil Statik, vol. 7, no. 12, Dec. 2019, Accessed: Aug. 05, 2023. [Online]. Available: https://ejournal.unsrat.ac.id/v3//index.php/jss/article/view/26145

T. Hamdy, Operations Research An Introduction. Pearson Education Limited , 2017. Accessed: Aug. 05, 2023. [Online]. Available: http://zalamsyah.staff.unja.ac.id/wp-content/uploads/sites/286/2019/11/9-Operations-Research-An-Introduction-10th-Ed.-Hamdy-A-Taha.pdf

R. Sinaga, P. Simanjuntak, and Setiyadi, “ANALISIS DAN PENERAPAN METODE LINE OF BALANCE PADA PROYEK REPETITIF,” Jurnal Rekayasa Teknik Sipil dan Lingkungan - CENTECH, vol. 2, no. 2, pp. 82–89, Nov. 2021, doi: 10.33541/cen.v2i2.3466.

S. A. Purba, “Analisis Jaringan Kerja dengan Metode Critical Path Method (CPM) dan Model Program Linier,” Jurnal Absis: Jurnal Pendidikan Matematika dan Matematika, vol. 4, no. 1, pp. 429–438, Oct. 2021, doi: 10.30606/absis.v4i1.993.

M. Nur’aini and K. Ikhsani, “Perencanaan dan Pengendalian Proyek dengan Metode CPM di PT Ghani Sejahtera Abadi,” SCIENTIFIC TIMELINE, vol. 1, no. 2, Sep. 2021, Accessed: Aug. 05, 2023. [Online].

M. Amiruddin, “PENGENDALIAN WAKTU PADA PROYEK PEMBANGUNAN LOS PASAR IKAN SEGAR GOTO KOTA TIDORE KEPULAUAN,” AKRAB JUARA, vol. 4, no. 4, pp. 40–55, May 2019, Accessed: Aug. 05, 2023. [Online]. Available: https://akrabjuara.com/index.php/akrabjuara/article/view/774

I. Mahapatni, METODE PERENCANAAN DAN PENGENDALIAN PROYEK KONSTRUKSI. Unhi Press, 2019. Accessed: Aug. 05, 2023. [Online]. Available: http://repo.unhi.ac.id/jspui/handle/123456789/186

A. Lubis, E. Suhendar, and P. Suharmanto, “OPTIMASI PENJADWALAN PROYEK PEMBANGUNAN JALAN TOL BECAKAYU SEKSI 1BC DENGAN MENGGUNAKAN METODE CPM DAN PERT,” Sustainable Environmental and Optimizing Industry Journal, vol. 3, no. 2, pp. 75–89, Sep. 2021, doi: 10.36441/seoi.v3i2.461.

L. Muzdalifah, E. Fitri Kurniawati, E. Deise Ulul, and K. Gular Pamitra, “PENJADWALAN PROYEK PERUMAHAN DENGAN OPTIMASI WAKTU DAN BIAYA HARIAN,” Jurnal Riset dan Aplikasi Matematika (JRAM), vol. 3, no. 2, p. 78, Oct. 2019, doi: 10.26740/jram.v3n2.p78-87.

V. Y. I. Ilwaru, D. L. Rahakbauw, and J. Tetimelay, “PENJADWALAN WAKTU PROYEK PEMBANGUNAN RUMAH DENGAN MENGGUNAKAN CPM (CRITICAL PATH METHOD),” BAREKENG: JURNAL ILMU MATEMATIKA DAN TERAPAN, vol. 12, no. 2, pp. 061–068, Dec. 2018, doi: 10.30598/vol12iss2pp061-068ar617.

H. Jay and R. Barry, Manajemen Operasi, 11th ed. Jakarta: Salemba Empat., 2014. Accessed: Aug. 05, 2023. [Online]. Available: https://api.penerbitsalemba.com/book/books/02-0302/contents/703c3330-4f78-498e-b9f2-99d1dfc021cb.pdf

H. Malayu and Estu Rahayu, Manajemen Sumber Daya Manusia. Jakarta: PT Bumi Aksara, 2014.

E. Larson and C. Gray, Project Management: The Managerial Process, 8th ed. McGraw Hill eBook, 2021. Accessed: Aug. 05, 2023. [Online]. Available: https://www.mheducation.com/highered/product/project-management-managerial-process-larson-gray/M9781260238860.html

N. M. Astari, A. M. Subagyo, and K. Kusnadi, “PERENCANAAN MANAJEMEN PROYEK DENGAN METODE CPM (CRITICAL PATH METHOD) DAN PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE),” Konstruksia, vol. 13, no. 1, p. 164, Dec. 2022, doi: 10.24853/jk.13.1.164-180.

A. Angelin and S. Ariyanti, “ANALISIS PENJADWALAN PROYEK NEW PRODUCT DEVELOPMENT MENGGUNAKAN METODE PERT DAN CPM,” Jurnal Ilmiah Teknik Industri, vol. 6, no. 1, Feb. 2019, doi: 10.24912/jitiuntar.v6i1.3025.

Published
2024-03-01
How to Cite
[1]
K. Santoso, A. Yusnita, and A. Pradjaningsih, “SCHEDULING ANALYSIS BEDUGUL VILLA CONSTRUCTION PROJECT USING PERT AND CPM METHODS”, BAREKENG: J. Math. & App., vol. 18, no. 1, pp. 0105-0116, Mar. 2024.